Год: 2019

The device of drilling and drilling piles with a diameter of 159 to 530 mm, a depth of 11 to 18 m.

This project is of great importance in the technological chain of the gas transmission system, on which the reliable supply of consumers with “blue” fuel depends. The station is designed to provide the required operating mode of the existing drying unit UKPG-2C and ensure the supply of gas to the existing system of main gas pipelines.
A distinctive feature of this compressor station is its design capacity – it is about 37.8 billion cubic meters of gas per year, which is achieved thanks to the presence of 7 powerful gas pumping units of 16 megawatts each. Ultimately, the launch of the station allows to significantly increase the capacity of the entire complex.